SP Field update
Published 12:00 am Friday, June 13, 2008

Eagle Golf and Athletics is making progress on the South Panola Field. Early this week they laid down the 57 limestone. Thursday or Friday, project manager Mike Eubanks was expecting to put down the 89 stone which is a smaller gravel. He reported some equipment repair that would delay them about half a day Wednesday but said they are still on schedule with the field. Photo by Mike Eubanks